GM: Overcoming Critical Supply Chain Disruption Through Rapid DC Deployment
Manufacturing
WSI Warehousing

GM: Overcoming Critical Supply Chain Disruption Through Rapid DC Deployment

subscribe

Stay Informed With the Latest Industry Insights

Join the TCG mailing list for industry news, capacity updates, and guidance from across the network. One email at a time, no noise.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
The Client

A global leader in the automotive industry, designing, manufacturing, and distributing vehicles and parts across a highly complex, global supply chain. The company must maintain consistent, reliable distribution performance to ensure production continuity and uphold service commitments across its network.

The Project

GM experienced significant operational challenges with its existing distribution providers, requiring an immediate short-term solution to stabilize operations and protect fulfillment performance and customer commitments.

Project Overview

The client experienced significant operational challenges with its existing distribution providers, putting fulfillment performance and customer commitments at risk. To avoid service disruptions, the client required an immediate, short-term solution to stabilize operations while a longer-term strategy was developed.

Project Type

Rapid distribution center deployment

Operational Focus

Emergency fulfillment continuity and inventory management

Performance Improvement

650,000 sq ft DC launched in 19 days

650,000
Sq Ft DC Launched
19
Days to Launch
100+
Associates Deployed
1,400
Trailers in First 90 Days

Execution Highlights

Rapidly establish and operate a fully functional distribution center

Ensure seamless continuity of order fulfillment and inventory management

Minimize disruption to customers and downstream operations

Outcomes

A fully operational 650,000-square-foot distribution center was designed, staffed, and launched in just 19 days, providing an immediate solution during a period of labor-related supply chain disruption.

Recruited, trained, and deployed more than 100 associates to support warehousing, inventory management, and distribution operations.

Processed approximately 1,400 trailers within the first 90 days while maintaining uninterrupted fulfillment operations and customer service continuity.

Approach

A fully operational 650,000-square-foot distribution center was designed, staffed, and launched in just 19 days, providing an immediate solution during a period of labor-related supply chain disruption.

Recruited, trained, and deployed more than 100 associates to support warehousing, inventory management, and distribution operations.

Processed approximately 1,400 trailers within the first 90 days while maintaining uninterrupted fulfillment operations and customer service continuity.

Enabled the company to maintain supply chain stability throughout the labor disruption, protecting customer commitments and preventing operational interruptions.

TCG stepped in at a critical moment and ensured our distribution operations continued without interruption during a highly challenging period.

Start with a Network Assessment

Bring us your current lanes, warehouses, or brokerage needs. The TCG team will map where TCG, WSI, or another of our services fits.

Get Started
Contact Us

Fill out the form and the right TCG team will reach out.

Thanks for reaching out. The TCG team will be in touch soon.
This is some text inside of a div block.

More Case Studies

      GM: Overcoming Critical Supply Chain Disruption Through Rapid DC Deployment
      Manufacturing
      WSI Warehousing

      GM: Overcoming Critical Supply Chain Disruption Through Rapid DC Deployment

      TCG designed, staffed, and launched a fully operational 650,000-square-foot distribution center for GM in just 19 days, maintaining uninterrupted fulfillment during a labor-related supply chain disruption.

      650,000Sq Ft DC Launched
      Read More
      TaylorMade: Expanding North American Distribution from a Central U.S. Location
      Retail Distribution
      WSI Warehousing

      TaylorMade: Expanding North American Distribution from a Central U.S. Location

      TCG expanded a central U.S. facility to approximately 310,000 square feet, consolidating TaylorMade's North American distribution operations in Evansville, Indiana.

      310,000Sq Ft Facility
      Read More
      SABIC: Enhancing Safety and Consistency Through Automated Bagging
      Manufacturing
      Specialty Services

      SABIC: Enhancing Safety and Consistency Through Automated Bagging

      TCG's automated palletization solution removed the need to manually palletize approximately 472,000 bags per year while achieving 99.9% pallet configuration compliance.

      472,000Bags Automated Per Year
      Read More
      Envalior: Reducing Costs and Improving Service Through Near-Site Distribution
      Manufacturing
      WSI Warehousing

      Envalior: Reducing Costs and Improving Service Through Near-Site Distribution

      TCG's near-site distribution center generated more than $7.0 million in transportation savings over five years while enabling uninterrupted just-in-time production for Envalior.

      $7.0MTransportation Savings Over 5 Years
      Read More
      Michelin: Improving Load Accuracy and Safety Through Upstream Audit Redesign
      Manufacturing
      WSI Warehousing

      Michelin: Improving Load Accuracy and Safety Through Upstream Audit Redesign

      By shifting audit responsibility upstream into the picking process, TCG generated approximately $347,000 in annual net labor savings for Michelin while improving load accuracy and dock safety.

      $347,000Annual Net Labor Savings
      Read More
      Case Study
      Manufacturing
      WSI Warehousing

      GM: Overcoming Critical Supply Chain Disruption Through Rapid DC Deployment

      The Client

      A global leader in the automotive industry, designing, manufacturing, and distributing vehicles and parts across a highly complex, global supply chain. The company must maintain consistent, reliable distribution performance to ensure production continuity and uphold service commitments across its network.

      The Project

      GM experienced significant operational challenges with its existing distribution providers, requiring an immediate short-term solution to stabilize operations and protect fulfillment performance and customer commitments.

      Download PDF
      GM: Overcoming Critical Supply Chain Disruption Through Rapid DC Deployment

      Project Overview

      The client experienced significant operational challenges with its existing distribution providers, putting fulfillment performance and customer commitments at risk. To avoid service disruptions, the client required an immediate, short-term solution to stabilize operations while a longer-term strategy was developed.

      Project Type

      Rapid distribution center deployment

      Operational Focus

      Emergency fulfillment continuity and inventory management

      Performance Improvement

      650,000 sq ft DC launched in 19 days

      650,000
      Sq Ft DC Launched
      19
      Days to Launch
      100+
      Associates Deployed
      1,400
      Trailers in First 90 Days

      Execution Highlights

      Rapidly establish and operate a fully functional distribution center

      Ensure seamless continuity of order fulfillment and inventory management

      Minimize disruption to customers and downstream operations

      Outcomes

      A fully operational 650,000-square-foot distribution center was designed, staffed, and launched in just 19 days, providing an immediate solution during a period of labor-related supply chain disruption.

      Recruited, trained, and deployed more than 100 associates to support warehousing, inventory management, and distribution operations.

      Processed approximately 1,400 trailers within the first 90 days while maintaining uninterrupted fulfillment operations and customer service continuity.

      Approach

      A fully operational 650,000-square-foot distribution center was designed, staffed, and launched in just 19 days, providing an immediate solution during a period of labor-related supply chain disruption.

      Recruited, trained, and deployed more than 100 associates to support warehousing, inventory management, and distribution operations.

      Processed approximately 1,400 trailers within the first 90 days while maintaining uninterrupted fulfillment operations and customer service continuity.

      Enabled the company to maintain supply chain stability throughout the labor disruption, protecting customer commitments and preventing operational interruptions.

      TC

      TCG stepped in at a critical moment and ensured our distribution operations continued without interruption during a highly challenging period.

      Start with a Network Assessment

      Bring us your current lanes, warehouses, or brokerage needs. The TCG team will map where TCG, WSI, or another of our services fits.

      Get Started

      More Case Studies

      View All →
      TaylorMade: Expanding North American Distribution from a Central U.S. Location
      taylormade-north-american-distribution